The design height of the device complex built for the addition of flue gas desulphurization facilities to No. 4 and No. 5 furnaces of Anqing Petrochemical Thermal Power Plant is 20.4 meters. At present, 11.4 meters of concrete construction has been completed. Reinforced steel plate formwork for 15.8 meters has been basically installed. Formwork reinforcement is being carried out. The entire device complex building is expected to be capped on April 5, about 10 days ahead of schedule for the original network plan on April 15.
Limestone silo silos and accident slurry tank foundation concrete construction of the project are proceeding as planned, and the booster fan foundation concrete has been poured.
Flue system bracket AH shaft, 1-11 axis in the construction process to overcome the underground area of ​​the production facilities complex conditions, difficulty in excavation, rain and other large-scale drainage difficulties, has completed 70% of the workload, all the work is also expected Completed by April 15.
The design height of the absorber tower is 27.2 meters, with a total of 14 layers. At present, 90% of prefabrication work has been done on the absorption tower system siding and attachments, and the installation of #9~14 siding and roof panels has been completed. At present, more than 60% of the total workload of the project has been completed.
In addition, in order to ensure that the follow-up installation work is proceeding in an orderly manner, the design drawings of the project and the desulfurization equipment on site are all strictly implemented according to the network plan.
Anqing Petrochemical key environmental protection renovation project, Anqing Petrochemical Thermoelectricity Department 4#, 5# furnace flue gas desulphurization facilities project has been started since December 15, 2009, the Anqing Petrochemical and other leaders at all levels attached great importance and the fighting units struggle Next, to overcome the difficulties of rain and snow and other inclement weather, all work was carried out smoothly according to the network node.